Latest News…April 13, 2020

Our Work Goes On…

During the past two weeks we’ve received many phone calls and emails asking if CFSIC was going to shut down or cease operations as a result of the COVID-19 crisis.

We have assured everyone who has contacted us that that’s not the case. Our great claim management team is terrifically busy…we get frequent reports from contractors about the progress of their remediation…and we are paying claims.

In fact, in the last two weeks alone we have paid more than $1.4 million in claims for Type 1 and Type 2 claimants.

We have pretty strong evidence that in the last two weeks of April scheduled construction will take off, particularly with the warm weather we’ve all been enjoying.

Many of the calls and emails we’ve received have been from claimants concerned that, with the great financial strain being placed on our state, we might not get our last two tranches of $20 million, and that in fact the Healthy Homes funds we have been promised at some point in June might never arrive.

We have no evidence that either of these things is going to happen. We can’t control the stuff that’s spread around on social media and elsewhere…the rumor, the innuendo, and the falsehoods…but the truth of what is going on with remediation can always be found on these pages.

Also, we have it on very good assurance that the current sunset date of June 30, 2022 will get moved to 2030, enabling our work to continue for the next decade.

It is true that the Superintendent is not signing any new Participation Agreements. That’s been true for some time, and has been written about many times on these pages. No new Participation Agreements will be signed until we see how much money we’re going to get…and, just as importantly, when we’re going to get it.

But to be clear, we have projects going on right now in many of the forty affected communities in the Northeast Corner, and our work goes on.

We have 378 signed Participation Agreements outstanding, of which 291 are Type 1 foundation replacements.

We now have 320 registered Pending claimants. We look forward to the possibility of moving each one of those claimants into line for assistance if and when further funds come to us.

Do we have 35,000 claimants? No. Do we have even half that number? No. But there is strong evidence that in this first “wave” of remediation, which we think will last through 2024, we probably will see as many as 2,500 registered claims; and when we get past all of the exaggeration about this crisis, and all of the politics, that kind of crisis is bad enough…because 2,500 eventual foundation replacements is $368 million in budget need. And let’s be clear: that‘s far more money than we expect to receive.

We have recently been asked by several town officials whether we could become involved in the looming infrastructure foundation crisis.

The current enabling legislation, as amended, does not permit this. Also, there’s the issue of funding as described above. But CFSIC’s record is clear about the management of the crumbling foundations crisis. Our underwriting and claims management protocols can easily be transferred, with applicable modifications, to infrastructure projects. Not only that, but we have a record of delivering services at a cost well below our statutory maximum expense allowance of 10% on a calendar-year basis.

Why “Do It Yourself” Is Not Allowed…

Under CFSIC’s Underwriting and Claims Management Guidelines, CFSIC divides foundation replacement construction work into allowable and non-allowable costs. These allowable and non-allowable costs are:

CFSIC’s allowable concrete (or other means of replacement) related costs, clearly outlined on this website, and calculated according to CFSIC’s linear and square footage calculations and further subject at all times to a cap per foundation of $175,000 (with the exception of condominiums). This is what CFSIC pays for.

Concrete (or other means of replacement) costs related to the replacement of a foundation…but where those specific costs are not CFSIC-allowable costs and therefore are not paid for by CFSIC.

Expenses related to the replacement of certain amenities that are neither allowable costs nor non-allowable costs under CFSIC’s program…CFSIC never pays for these costs.

All CFSIC pays for is allowable costs…and according to CFSIC’s rules.

Any claimant wishing to understand this process better should go to the “For Homeowners” section of this website, and specifically to sub-sections #2 and #3.

CFSIC requires a minimum of two contractor proposals in order to approve a foundation for remediation. These proposals can only be supplied, under the CFSIC program, by construction firms approved by CRCOG and the committee overseeing contractors vetted for the program.

As a result, CFSIC will not permit homeowners or others not on CRCOG’s approved list of contractors to provide any allowable construction work or services.

Said simply, any homeowner who wants to take a “do it yourself” approach to their own foundation replacement needs to understand that if any of the “do it yourself” work is work that would normally be performed by an approved contractor as an allowable cost and paid for by CFSIC, CFSIC will immediately cancel the project if this occurs, or will not approve the project to begin with if that activity is contemplated. Contractors know this is our rule, and they will not help you participate in this process.

Again, CFSIC requires that the complete construction contract for services be a part of the claimant’s file. We need that information. And with respect to what is defined as allowable costs within the CFSIC program, at no time can homeowners provide their own construction services…even for free.

Governor Lamont’s Executive Order No. 7H

We wanted you to know that under Governor Lamont’s Executive Order signed on March 20, regarding restrictions on workplaces for non-essential businesses, CFSIC is in fact considered an essential business.

CFSIC is an insurance company. It is licensed and regulated by the CT Insurance Department. It will continue to operate, as insurance companies are considered to be essential businesses under the Governor’s Executive Order of March 20. All staff involved in CFSIC’s efforts is fully engaged in day-to-day operations. All staff is working remotely, has access to claim files and other information, and is processing construction progress payments, initial deposits, and generally taking care of business, including the intake of pending claim information.

We also want to advise you that it is our belief that the CRCOG-approved contractors able to provide foundation construction services are, based on our reading of the Governor’s Executive Order, also considered essential businesses. Our belief is that they may continue with the work of foundation replacement.

However, the coronavirus pandemic is a life-threatening and life-changing event.

We have communicated with all contractors currently on CRCOG’s list to advise them that, to the extent they want to discontinue any work they are doing because of concerns about worker safety, they should contact homeowners directly with whom they have contracts in place and for whom work is underway.

They then should contact ESIS promptly about their planned suspension of construction activities during the crisis.

The ESIS team, assisted by the Superintendent’s office, will take all necessary steps to transfer construction responsibilities, where possible and applicable, to other contractors continuing to provide services during the crisis.

ESIS can be reached by email at cfsic@esis.com or by phone at (844) 763-1207.

The Superintendent’s office can be reached at 860-487-0000.

Homeowner Claimant Responsibilities During the Crisis

CFSIC’s Board believes that each of us must act responsibly and thoughtfully during this crisis.

This means following the guidance and directives of government officials at all times, remaining at home, practicing hand hygiene, and observing social distancing mandates.

With regard to the work that CFSIC is doing…homeowner claimants have another responsibility:

at this time of crisis, which may shortly become a time of financial crisis, we want to remind homeowners of the critical need to observe and monitor the foundation remediation work being done on their homes…as that work is being done.

Claimants should not only observe the progress of work, but should also ask questions about what they see and, as appropriate, involve town building officials, asking for their advice and guidance about the work being performed, and the timeliness and quality of work undertaken on their homes.

Lastly, and by way of important reminder, CFSIC will not authorize a progress payment to a contractor for foundation work until a homeowner has already paid their share of that progress payment. The homeowner’s share of any progress payment is set forth in the construction contract, which is a material part of the claimant’s Participation Agreement. If you don’t pay…we don’t pay.

Said simply, homeowner claimants should not make work progress installment payments for their share of any installment without understanding exactly what has occurred by way of progress on the project, and being satisfied with it.

If you are dissatisfied with the progress of work, or you have questions or concerns about the work performed, if the contractor is late in showing up for your project, or not responding professionally to your requests for information about the status of your foundation remediation, CFSIC believes that your first source of good information and potential resolution is always the contractor doing the work.

You also have available to you town building officials, who can advise you upon your request.

CSFIC will not authorize a progress payment to a contractor is there is a dispute of any kind between a homeowner and a contractor in the course of a project.

This process depends, however, on your communication with us.

We don’t know what we’re not told. Tell us what’s going on. We are depending upon homeowners to be our eyes and ears in the field.

We are all going to come out of this crisis at some point, and we will tell you normal life will return to us all. When we do, we want dozens of foundations replaced and dozens of families back in their homes without incident.

Further Extension of Pending Claimant Filing Through June 30, 2020

We’re pleased to announce that, after some reconsideration of our current capabilities to handle additional application flow and a re-calculation of the number of actual potential pending claims we have received, we will continue to accept pending claimants through June 30, 2020.

This will give more claimants an opportunity to prepare applications and to post points of evidence in a way that will enable more claimants to enter our system.

Participation Agreement Suspension in Place

We have suspended the issuing of new Participation Agreements, and we will not resume Participation Agreement activity until at some point after July 1, 2020.

If you have not yet been provided with a Participation Agreement by the Superintendent’s office by now, you will not hear anything more about your Participation Agreement until we resume issuing them.

You are still in line. We haven’t lost you. We haven’t forgotten about you. We are all going to find out together and pretty much at the same time when CFSIC will be able to resume Participation Agreement activity. We are at a point within CFSIC where we must conserve our remaining cash until two things happen:

  • we identify exactly how much funding CFSIC will receive from the $12 per homeowner policy surcharge; and
  • we receive our next $20 million bond allotment from the CT Bond Commission.

Without knowing, with precision, the facts about when we will receive these two sources of funding, and in the case of the $12 homeowner policy surcharge, exactly how much we are getting, we will not be issuing any further Participation Agreements until this website announces further information.

A Message to Severity Class 2 Claimants

We have a total of 179 claimants with Severity Class 2 foundations on our books.

174 of those claimants are active claimants. We hold financial reserves on them right now of $22,269,158.

Many of those claims represent applications that go back to the earliest days of our operations; and we know that Severity Class 2 claimants want and need answers about when we can get to them, how long it’s going to take, and whether will we have the money to fund their claims.

CFSIC’s board is very keenly aware of all of the concerns of our Severity Class 2 claimants.

As of this morning, we have created a new subsection in the “For Homeowners” section of this site, specifically designed for Type 1, Severity Class 2 claimants.

View a comprehensive Q&A specifically designed to answer questions about Severity Class 2 claims.

CFSIC Has Resumed Application Activity

CFSIC began taking applications again effective 9:00 AM on January 13. We have re-opened the electronic platform to accept applications for claimants who agree to be placed in “Pending” status, and we have also enabled applications to be sent to the ESIS team by mail or other means.

CFSIC will remain open for the taking of applications through close of business on March 31.

To be clear, any claimant making claim to CFSIC on or after January 13 will be placed in “Pending” status. This means that your claim will be neither active nor inactive, regardless of the severity class code assigned to your foundation. CFSIC will not place a statutory financial reserve on your Pending claim until and only if we determine that we have sufficient funds to move any or all Pending claims into either inactive or active status.

What follows are some links that will take you to where you need to go:

View a video that will help you complete an electronic application.

Apply as a Type 1 (foundation replacement) claimant.

Apply as a Type 2 (foundation reimbursement) claimant.

The following Q&A should help everyone understand what is happening on January 13.

Question: I’ve been waiting for you to reopen your doors. I have a verified severity class coded 3 foundation, and I want to apply as a Type 1 claimant. I’m going to apply right away on January 13. What will happen to my claim?

Answer: You will become a “Pending Claimant” in our system. That means that we are creating a third category of claimant effective January 13, 2020. Right now, CFSIC only permits a claimant to be “active” or “inactive.”  On January 13, you will only be able to file as a claimant under the new third status of claimant…a Pending Claimant. This means that we will register your claim and all the data you send us. We will provide you with a claim number, and we will acknowledge your claim…BUT even if you have a verifiable severity code 3 claim, you will not be able to move out of Pending status to either inactive or active status unless and until CFSIC’s sunset date is moved forward beyond June 30, 2022 AND we determine, starting in June of 2020, what the most likely scenario is for the amount of money we will receive from our share of the Healthy Homes surcharge.

Question: Are you saying that, even if I have a completed application and a verified severity class code 3 foundation, you will be unable to make my claim “active” or even “inactive” on or after January 13?

Answer: That’s correct. You will not be able to be an active or inactive claimant until the two things above are determined. You will be a Pending Claimant. You may remain a Pending Claimant for a very long time.

Question: That doesn’t seem fair. Why is it happening that way?

Answer: Because, until the June 30, 2022 sunset date gets moved to a later date AND we actually see exactly how much money we are getting in June 2020 from the Healthy Homes surcharge, we are flying blind…we can’t set any more claim reserves on any new claims beyond what we’ve already done. If we do that, we run the risk of making promises to claimants on or after January 13 that we can’t fulfill.

Question: So if the sunset gets moved to, say, June 30, 2030 (the end of the Healthy Homes surcharge funding schedule)…are you saying that you will permit claimants who applied on or after January 13 to become active?

Answer: We’re almost saying that…the sunset date is only part of our problem. You have to remember that no one inside or outside of state government can tell us specifically how much revenue we’ll be getting from the Healthy Homes surcharge (just like no one inside or outside of state government can tell us when our next $20 million will be available to us from the CT Bond Commission). We must have time to evaluate both critical sources of revenue in order to make the best decision for homeowners.

Question: But don’t you know for certain that you’re getting approximately $8.5 million in June of 2020 and every year thereafter through June 30, 2030?

Answer: That’s the estimate…but it’s only an estimate. That could be the number. The number could be higher. The number could be considerably lower. No one can tell us.

Question: So if the sunset date gets moved, you get enough money in June of 2020, and you make my Pending Claim an active claim, and I am a severity class 3, that means I jump ahead of all the existing severity class 2s that have been in line since last year…right?

Answer: No. As of January 13, 2020, we are not going to permit any severity class 3 claim originally filed as a Pending Claim to jump ahead of an active severity class code 2 already registered with us as an active claim prior to January 13, 2020. We have many active severity class coded 2 claimants who have been in line since January of 2019, and we have determined that it is fair to issue Participation Agreements first for all existing active 3s and 2s in our system before any Pending Claimant can get in line for a Participation Agreement. This is only fair, given how long people have waited and the fact that we are only going to get $40M more in funding over the next two years from the CT Bond Commission source…and on top of that, we have virtually no idea how much we will get in Healthy Homes surcharge funds.

Question: But I thought severity class coded 3 claimants would always be ahead of everyone else. What has changed?

Answer: CFSIC’s Underwriting and Claims Management Guidelines will change effective January 13, 2020 to require that CFSIC issue Participation Agreements to valid, active severity coded 3 and 2 claimants who have been in line since the inception of our program before we move any other Pending claimants into active or even inactive status…regardless of funding amounts to come. If you file on or after January 13, we will have a record of your claim, and we will also have significantly more data about the extent of the crisis…but we’re not going to be able to do anything with your claim until the sunset date gets moved and we have evidence of a flow of predictable funds from the surcharge.

Question: How long are you going to keep the application process open from January 13?

Answer: A minimum of 30 days, but we don’t know exactly how long yet beyond that.

Question: Why don’t you know?

Answer: CFSIC’s fiscal year budget in the year July 1, 2019 through June 30, 2020 is finite. When claims enter our system, we are charged by our outsourced claims management service company on a per-claim basis, as each claim is entered into the system, is analyzed, and is assessed. We have enough budget for the remainder of the fiscal year for a reasonable number of claims to enter our system between now and June 30, 2020…but not for a significant number to enter our system.

Question: But can’t you make an educated guess as to the number of people who are going to apply on or after January 13?

Answer: No, we can’t. Just before we opened our doors on January 10, 2019, we were told by email and through social media sources that we would get as many as 7,000 applications and that our application system would crash. We got 227 on the first day. We have found, through experience, that the wild projections as to application activity were then and may continue to be exaggerated. The reality of people actually taking action is unknown. We hope to have many new Pending Claimants, which will send a strong message about our need for funding. But to be clear, we will all see together what we will see…when we all see it.

Question: I want to apply as a Type 2 claimant. Will all the same rules apply to me?

Answer: Yes. (With one exception: Type 2 claimants do not require a severity class coding.)

Question: This all seems like a lot of work just to get in line and have my claim be in pending status for what might be a really long time. Is all this worth it?

Answer: That’s totally up to you. We’re giving people an opportunity to give us the data we need to raise more funds by identifying more potential claimants, who we hope to be able to assist at some point in the future when those funds arrive. We’ve gotten emails asking us to re-open for this purpose. We’re doing it. The question now will be how many victims of this crisis will actually take us up on our offer: file a claim, get in line, and with their claims registered…send a strong message about our need for more funding.

The CHFA Credit Enhancements Program

You should go here to learn more about the CHFA credit enhancements program as it is now constituted. Please note that it currently does not apply to condominiums. CFSIC did not create and is not administering the loan program, and the ESIS claim team cannot advise you in any way about the terms and conditions of any aspect of the program. The link noted in this section will take you to an outline of the program, as well as to a section marked “Frequently Asked Questions.” We also recommend contacting the Homeowner Advocate using the contact information on the Department of Housing website for more assistance.

CFSIC’s Annual Report

CFSIC’s Annual Report can be viewed here. 

CFSIC’s 2019 Audited Financial

View CFSIC’s audited financial report for the period ended June 30, 2019.

___________________

If you have any questions about the operation of the program, ESIS is your best source of information on your claim, and their phone number and email are shown below.

Phone: 844-763-1207

Email: cfsic@esis.com

As you work through the information and application process (understanding that we are in suspension for the taking of new applications), here’s how you can get help:

– Call ESIS (the claim adjuster) at: 844-763-1207

– Email ESIS at: cfsic@esis.com

– Email CFSIC at: info@crumblingfoundations.org

To view a video of how to complete an electronic application, go here.

To apply for a Type 1 claim, go here.

To apply for a Type 2 claim, go here.

To learn more about the program, if you are a homeowner, including application help (once we are out of suspension for the taking of new applications), go here.